Quick answer
The supply is a normal single-phase house fuse. The heat pump, the car and the battery all want the same cheap hours. Something has to wait, and the quote should say what.
The kit already promised
The house is outside Exeter, on National Grid Electricity Distribution. It has a 100 A single-phase supply, an air-source heat pump, a 7 kW charger on the drive, and a plan for a 10 kWh battery with a 5 kW inverter. The roof is 5 kWp, clear and south-facing, which in Devon is a decent array.
On paper the fuse is 100 A, about 23 kW. That number is not a budget you can spend all at once. Diversity, the heat pump's start, the charger and the battery charge can still clash, and the network is entitled to care about the generation side as well.
The 5 kW inverter needs a G99 application (network permission before switch-on). The charger was already notified on its own. Adding the battery does not cancel that. The designer has to look at the site as one supply, not as three purchases.
The cheap window is not wide enough
The household is on a tariff with a cheap overnight window of a few hours. In that window the heat pump would like to run, the car would like 7 kW, and the battery would like 5 kW. Added together that is already a heavy slice of the fuse, before the fridge and the standby loads.
A 10 kWh pack at 5 kW needs about two hours from empty, longer once you allow for losses and a reserve. If the car is also due a full overnight charge, the car wins on most weeknights, because the owner has to drive. The battery then starts the morning half empty and the solar has to finish the job.
In December the array will not finish it. The heat pump will be the largest load in the house. A battery sized to 'cover the heat pump all evening' will not, unless someone has done the watts rather than the slogan. A 10 kWh pack can shift a slice of the evening. It cannot replace the pump.
A written priority
The design that went forward names a priority. The heat pump keeps its own control and may run in the cheap window. The charger is limited when the pump and the battery are both drawing. The battery charges from surplus solar first, and takes overnight grid only when the car is above the miles the owner set.
That needs a load management device or an inverter and charger that can see each other. A battery quote that assumes the charger is 'someone else's problem' will be wrong the first cold Monday.
The owner wanted backup for the pump as well. The survey declined it. A heat pump on a gateway, through a power cut, is a large continuous load and a poor use of 10 kWh. Backup, if they still want it, is the fridge, the router and the heating controls, not the pump itself.
What the quote should show
One line for the battery and inverter. One line for G99. One line for load management with the existing charger. One line that says the heat pump is not on the backup circuits. The roof stays as it is, so there is no scaffold in this particular job.
Usable kilowatt-hours, not the badge, go on the schedule. If the usable figure is 9 kWh after the reserve, the overnight arithmetic uses 9.
Devon yield makes the summer easy to like. The supply limit and the winter pump are what the survey is actually deciding. A quote that leads with June generation and never mentions the charger is describing a different house.
Frequently asked questions
Would three-phase remove the clash?
A three-phase supply gives more room, and it is a different connection with its own cost. It is not a casual upgrade. On this house the single-phase supply can work if the three loads take turns.
Can the battery charge the car in a power cut?
Not in any design that was sensible here. The car is a large load, the cut may last longer than the pack, and running the charger off-grid (islanding) needs its own design. Backup was limited to small circuits.
Who tells the network about the battery if the charger was already agreed?
The battery installer still applies for the generation. The existing charger paperwork does not cover a 5 kW inverter. Ask to see a G99 reference that names this inverter.
Get battery quotes in Exeter
Figures here are a guide. An installer still needs to see your fuse board, where the battery will go and whether you want backup. Tell us your postcode and local installers will quote.