Quick answer

G98 is connect and notify: every inverter is type tested, the total is 16 amps per phase or less (3.68 kW on a single-phase supply), and the installer tells the network operator within 28 days of commissioning. Anything larger comes under G99. Most home systems above the G98 limit now use one of three G99 fast track procedures, SGI-1, SGI-2 or SGI-3, and only the last two need approval before installation.

  • G98: 16 A per phase in total, notify within 28 days after commissioning
  • A battery inverter is added to any solar inverter already there
  • G99 SGI-1: install first, then notify on Form A3-3
  • G99 SGI-2 and SGI-3: apply on Form A1-2 and wait for the answer
  • Fast track answers come within 10 working days; a standard application can take 45

What the two documents are

G98 and G99 are engineering recommendations published by the Energy Networks Association. They set the technical and paperwork rules for connecting anything that generates electricity to the local network in England, Scotland and Wales. Northern Ireland has its own versions, G98/NI and G99/NI, run by NIE Networks.

A home battery counts as generation because it can push power back into the house wiring and the grid. So does a solar inverter. The rules look at every such unit at the property together, old and new. That is the detail that surprises people: a 3.6 kW solar inverter and a 3 kW battery inverter are each small, but together they are 6.6 kW.

The company that receives the paperwork is the distribution network operator, or DNO, which owns the local cables and substations. It is not your energy supplier. Use the DNO lookup to find yours.

The numbers that decide the route

Everything turns on amps per phase, worked out from each inverter's rated output at 230 volts. On a single-phase supply, which most homes have, 16 A is 3.68 kW and 32 A is 7.36 kW. On a three-phase supply the same limits apply to each phase, so a three-phase inverter of 11.04 kW is 16 A per phase.

Three figures matter. The first is the largest single unit. The second is the total of all units. The third is whether an export limitation scheme, type tested to a further standard called G100, caps what the home can send out.

One refinement arrived with the current edition of G99. An inverter can have a design capacity above its registered output if the manufacturer has limited it. A 5 kW inverter supplied with its output fixed at 3.68 kW has a design capacity of 21.7 A and a registered capacity of 16 A. The rules treat those two numbers separately.

G98 and G99 procedures for homes, in amps per phase
ProcedureTotal of all unitsApproval before installing?Form
G9816 A or less, each unit 16 A or lessNo. Notify within 28 daysG98 Form B
G99 SGI-116 A or less, with a unit whose design capacity is up to 32 A but limited to 16 ANo. Notify after installationForm A3-3
G99 SGI-2Under 32 A, each unit 16 A or less, export limited to 16 AYes. Result within 10 working daysForm A1-2
G99 SGI-3Under 60 A, each unit's design capacity 32 A or less, export limited to 32 A unless the total is 32 A or lessYes. Told within 10 working days if more analysis is neededForm A1-2
G99 standardLarger, not type tested, or with island modeYes. Up to 45 working days for an offerForm A1-1

G98: connect and notify

If every inverter is fully type tested and the total is 16 A per phase or less, the installer fits the system and then sends the network operator an Installation Document, which is Form B in G98. The deadline is 28 days from commissioning, counting the day of commissioning itself. There is no application and no fee.

The form records the customer, the installer and their accreditation, the supply number (MPAN), where the equipment and its isolator are, and a line for each inverter with its reference on the ENA Type Test Register. The installer signs a declaration that the installation conforms to G98. Where the notification goes through the ENA's Connect Direct portal, a clear photograph of the cut-out, the sealed fuse where the supply enters the house, has to go with it.

The duty to notify sits with the installer. Regulation 22 of the Electricity Safety, Quality and Continuity Regulations 2002 puts it on the person installing the equipment. Your job as the owner is to make sure you receive a copy of the acknowledgement. Some network operators ask for more: SSEN's G98 page says you must apply before connecting if there is more than one generator at the property, which includes a battery added to existing solar, so check your operator's page first.

The G99 fast track: SGI-1, SGI-2 and SGI-3

G99 used to mean one slow application for anything over 3.68 kW. The current edition adds three Small Generation Installation procedures for homes where every inverter is type tested and no unit has a design capacity above 32 A.

SGI-1 covers a larger inverter whose output has been limited to 16 A, with a total still at 16 A or less. It works like G98: install, then notify, on Form A3-3. The limit is set by the manufacturer and cannot be raised later without a fresh application.

SGI-2 covers a total under 32 A where each unit is 16 A or less and a G100 scheme holds export to 16 A. This is the common route for adding an AC coupled battery to an existing small solar system. You apply on Form A1-2 with a single line diagram and a description of the export limitation scheme, and the network operator gives its result within 10 working days.

SGI-3 covers a total under 60 A, with export limited to 32 A unless the total is already 32 A or less. A single 5 kW or 6 kW hybrid inverter lands here. You apply on Form A1-2, and within 10 working days the network operator says whether it needs to study the local network. If it does, it then decides whether the network needs upgrading and whether you would be charged.

Under SGI-2 and SGI-3 nothing should be installed or commissioned before the network operator answers. The commissioning date on the form must fall between 10 working days and 3 months after you apply, and the installer confirms commissioning on Form A3-2 within 28 days.

When the fast track does not apply

A system falls back to a standard application on Form A1-1 if a unit has a design capacity above 32 A, if the total reaches 60 A, if an inverter is not on the Type Test Register, or if the total is above 32 A with no export limitation scheme. Form A1-1 covers totals under 17 kW on a single phase and under 50 kW on three phases.

Backup matters too. The ENA's connection guide says the fast track does not apply where storage is designed to run in island mode, for example powering the house during a power cut, and that the standard process applies. If you want backup power, tell the installer early so the right form is used.

For a standard application the network operator has up to 45 working days to make an offer for a low voltage connection. It can charge assessment and design fees and the cost of any upgrade. Ask what the fee is before applying.

  • Design capacity of any unit above 32 A per phase
  • Total of all units at 60 A per phase or more
  • An inverter that is not fully type tested
  • More than 32 A in total with no G100 export limit
  • Storage that can run the home in island mode

How each network operator takes the forms

The rules are national but the front door differs. UK Power Networks uses its Smart Connect portal and says only installers can notify it on behalf of customers. National Grid Electricity Distribution has one online form for applications and notifications, which it says takes 15 to 20 minutes, and also takes the forms by email. SSEN takes fast track forms by email and asks for loop impedance measurements with an SGI-3 application.

Northern Powergrid, Electricity North West and SP Energy Networks publish their own versions of the forms on their connection pages. See the guides for UK Power Networks, National Grid, SSEN, Northern Powergrid, Electricity North West and SP Energy Networks.

Whichever route applies, the G98 or G99 route finder works out your procedure from the inverter sizes, free, and can prepare the form data, evidence checklist and letters for it.

Why the reply matters after the installation

The network operator's acknowledgement is not a formality. SSEN notes that most suppliers require the DNO's response before you can apply for an export tariff, and the supplier has to ask the network operator to create an export MPAN for your meter. See the Smart Export Guarantee.

It also follows the house. A buyer's solicitor can ask for proof that the system was notified, and a later upgrade is assessed against what the network operator already holds for the address. Keep the acknowledgement with the installation certificate and the system schematic.

If you have a system and no proof it was ever notified, ask the installer first, then ask the network operator what it holds for your MPAN. A missing notification can usually be put right, but it needs a competent installer to sign the form.

G98 and G99 paperwork

Not sure which form your system needs?

The free route finder works out whether your solar or battery is G98, or G99 SGI-1, SGI-2 or SGI-3, from the inverter sizes. The £19 pack then fills in the form data, the evidence checklist and the letters for your network operator.

Frequently asked questions

Is 3.68 kW the limit for a home battery?

It is the limit for the simplest route, not for the battery. 3.68 kW is 16 A on a single phase, the G98 ceiling for all inverters at the property combined. Larger systems are allowed. They use a G99 procedure, and many qualify for the fast track.

Does battery capacity in kWh affect G98 or G99?

No. The rules look at inverter output in kW, converted to amps. A 5 kWh battery and a 15 kWh battery on the same 3.6 kW inverter are treated the same. The kWh figure is recorded on the form but does not change the route.

Do I need DNO approval to add a battery to existing solar?

Often, yes. The battery inverter is added to the solar inverter. If the two together exceed 16 A per phase you are in G99, and unless the system fits SGI-1 the network operator must answer before the battery is installed. A hybrid inverter that replaces the old one may keep the total lower. Check your own network operator's rules as well: in an SSEN area a second generator at the address, such as a battery beside existing solar, needs an application before it is connected even under the G98 limit.

How long does G99 approval take?

On the fast track, the network operator responds within 10 working days of a complete application. A standard application on Form A1-1 can take up to 45 working days for an offer. Missing attachments are the usual cause of delay.

What is G100?

G100 is the standard for export limitation schemes, which measure the power leaving the home and hold the inverters back so export stays under an agreed limit. SGI-2 needs a G100 scheme set to 16 A per phase. SGI-3 needs one set to 32 A unless the total is already 32 A or less.

What happens if a system is installed without telling the DNO?

The network operator has no record of it, which can block an export tariff and raise questions when the house is sold. The regulations also let a network operator disconnect an installation that does not comply. It is normally fixed by notifying or applying retrospectively.

Can I apply myself?

The forms carry an installer's declaration and signature, and UK Power Networks only accepts notifications from installers. In practice the installer submits. You can still check which route applies, supply complete details and insist on a copy of the reply.