The useful part of a home battery survey is not the brochure left on the kitchen table. On this Headingley terrace it was a tape, a phone photo of the consumer unit, and a blunt conversation about the stairs.
09:10, the street before the cupboard
The house is a stone terrace off a Headingley side street. There is no driveway. The surveyor parked two doors down, which already matters, because an 80 kg cabinet does not float from the van to the hallway.
The owner had a quote from a national package that assumed a garage. This house has never had one. The first five minutes were spent walking the carry route: front step, narrow hall, a turn at the bottom of the stairs, then a utility that used to be a coal store.
Northern Powergrid covers Leeds. The survey did not phone them yet. It did write down that any inverter over 3.68 kW would need a G99 application (the network permission process for larger generators) before anyone switched it on. The package quote had skipped that line.
The consumer unit under the stairs
The board is a 1990s metal consumer unit (the fuse box) with one spare way, meaning one free slot for a new circuit. The main fuse is 80 A, not the 100 A figure printed on the other company's drawing. That single number changes how hard a charger, a battery and a kettle can pull at once.
The surveyor photographed the board with the cover on, then asked permission before removing it. Labels were faded. The shower and the cooker were identifiable. One circuit was marked 'loft' and nobody in the house knew what it fed.
There was no room for a backup gateway and a battery in that same under-stair void. The owner wanted the lights on in a power cut. The surveyor said that was a second design, with an essential-load list of circuits that stay on, not a tick box on the first quote.
Where the cabinet would actually sit
The utility is cool, which LFP (lithium iron phosphate) cells prefer, and it is not an escape route. The door opens onto the hall and would have hit a cabinet placed where the brochure photo suggested. The tape said the clear opening was 540 mm. The datasheet wanted more in front of the unit they had been shown.
A smaller pack fitted. The 13.5 kWh cabinet did not, unless they moved the washing machine and accepted a door that no longer closed. They chose the pack that left the door working. That is a boring decision and it is the one that survives the first winter.
The loft was offered as an alternative. It is a finished room used as a study, and it sits under a dark slate roof that cooks in June. The surveyor declined it. A hot loft is a siting fault, even when the cable run to the board is short.
The roof they already have
There is a 3.6 kWp array from 2018, with a string inverter (solar-only box) in the utility and a generation meter still in its original place. The inverter has no battery port. The choice was an AC-coupled pack beside it (a separate battery inverter on the house wiring), or a hybrid swap that would replace the solar inverter and disturb the generation meter.
Because the solar was registered for the Feed-in Tariff (the old export payment scheme, often called FIT), the surveyor would not let a new inverter sit where battery discharge could be counted as generation. The AC-coupled option left the old inverter and the meter alone. That was the point.
Shade from the neighbour's extension kills the array by mid-afternoon in March. A bright June day can still fill a modest pack. A January week will not. The surveyor wrote 'overnight top-up required' on the sheet so nobody later pretended the roof would do the winter on its own.
What left the house in writing
The survey sheet named the cupboard, the spare way, the 80 A fuse, the existing inverter make, the generation meter, and the carry from the kerb. It also named what was excluded: no gateway, no new consumer unit, no scaffold, because nobody was getting on the roof that day.
The owner had wanted one number. They left with two. One was supply and fit of the smaller pack on the existing inverter. The other added a board change if the spare way turned out to be unusable once the cover was properly identified.
That is what a survey is for on a terrace like this. The street is ordinary. The coal store, the fuse and the FIT meter are not. A national price that ignored all three was not a quote for this house.
Frequently asked questions
Did they need scaffolding just to price a battery?
No. The array was already up and the inverter was staying. Scaffold would have appeared only if someone was adding panels or replacing roof kit. The survey looked at the electrical end and the cupboard.
Why refuse the larger cabinet?
The door would not have shut, and the datasheet clearance in front of the unit was not there. A battery you cannot service, or a utility you cannot use, is a failed install even if the app looks tidy.
Who applies to Northern Powergrid?
The installer, before the system is switched on if the inverter is above the G98 connect-and-notify limit (usually 3.68 kW). The homeowner should see the application reference on the paperwork, not hear that it will be sorted later.