Quick answer

SSEN home battery packs are portable power stations that SSEN Distribution gives free to some Priority Services customers who depend on electricity for medical equipment; you cannot apply, and SSEN contacts eligible people itself. They are not a grant towards a fitted home battery. If you are fitting a home battery in an SSEN area, the installer either notifies SSEN on G98 Form B within 28 days of commissioning or applies under the G99 fast track, where SSEN aims to respond within 10 working days. A battery added to existing solar counts as a second generator, which SSEN says needs an application before connecting.

  • The packs are EcoFlow Delta 3 units of 1,024 Wh, free to eligible Priority Services customers
  • There is no application: SSEN assesses need and contacts people when it is their turn
  • SSEN runs two licence areas: the north of Scotland and central southern England
  • G98: Form B to microgen@sse.com within 28 days of commissioning
  • G99 fast track: apply to G99FastTrack@sse.com and wait for SSEN's answer, which it aims to give within 10 working days
  • A battery added to existing solar counts as a second generator, which SSEN says needs an application first

What SSEN home battery packs are

The phrase comes from a real SSEN scheme. In February 2026 SSEN Distribution began handing out home battery packs to Priority Services customers who are medically dependent on electricity. Its news release of 24 February 2026 describes the first of 20,000 packs being delivered, and says 94% of the people offered one since the launch earlier that month had accepted. SSEN's scheme page, checked on 27 November 2026, says more than 11 thousand customers have accepted the offer.

The pack is an EcoFlow Delta 3, a portable power station rather than a wall battery. SSEN lists it at 1,024 Wh, with USB-A, USB-C and three-pin sockets, just over 12 kg, and 398 by 200 by 284 mm. It is charged from a normal socket and used during a power cut to keep phones, laptops, a broadband router or a light going. SSEN says some medical devices may run for longer on it, subject to the device maker's approval.

You do not apply for one. SSEN says it assesses each customer's needs when they join Priority Services, together with how often power cuts happen in their area, and contacts eligible customers when it is their turn. The scheme grew out of a six-month trial with 28 people who rely on powered medical equipment, and the packs in the wider rollout have a third more capacity than the trial units.

  • Who: Priority Services customers who are medically dependent on electricity, chosen by SSEN
  • Cost: free to eligible customers
  • How: register for Priority Services; SSEN makes contact, there is no form
  • What it is not: a grant, a fitted battery, or anything that needs DNO paperwork

If you meant a fitted home battery

Most people searching SSEN and home batteries are planning a fixed battery, usually beside solar panels, and want to know what SSEN has to approve. A fitted battery is a different thing from the free packs. It connects to the house wiring through an inverter that can push power into the network, so SSEN, as the distribution network operator, has to be told about it or approve it first.

The rules are the national ones, G98 and G99, which are explained in G98 and G99 for home batteries. What SSEN adds is its own front door: which form, which email address, what it wants attached and how quickly it says it replies. Those details are below.

If power cuts are the reason you want a battery, note that a standard grid-tied battery turns off with the grid. Backup needs a gateway or an essential-load circuit designed in, and storage built to run the house in island mode falls outside the fast track. See will a battery work in a power cut.

The two SSEN licence areas, and how to check yours

SSEN Distribution holds two distribution licences. Scottish Hydro Electric Power Distribution plc covers the north of Scotland and Southern Electric Power Distribution plc covers central southern England. SSEN says that together they deliver power to over 3.9 million homes and businesses, with teams based in Reading, Portsmouth, Perth and Inverness.

In practice the north takes in places such as Aberdeen and Inverness, and the south places such as Oxford and Southampton. The rules are the same in both, but notifications go to different inboxes, so the installer has to know which side of the business the address sits in. The two areas are also very different solar sites, so a yield figure from one should not be used to sell a battery in the other.

To check, enter the full postcode in SSEN's own distributor lookup, the Energy Networks Association's postcode search, or our DNO lookup. Addresses near a boundary can fall either side, and some new estates sit on an independent network instead, so confirm before any form is sent.

SSEN's two licence areas
Licence companyAreaInstaller notifications
Scottish Hydro Electric Power Distribution plcNorth of ScotlandNotifications.northmicrogen@sse.com
Southern Electric Power Distribution plcCentral southern EnglandNotifications.southmicrogen@sse.com

G98 or G99 for a battery on SSEN's network

The dividing line is inverter output, not battery size in kWh. G98 covers type tested generation totalling 16 A per phase or less, which is 3.68 kW on a single-phase supply. Anything above that is G99, and most homes use one of three fast track procedures that SSEN sets out on its G99 fast track page.

SSEN's G98 page says you must apply before you connect if there is more than one generator at a single property. A battery added to an existing solar system is a second generator, so in an SSEN area that job should be treated as an application even if both inverters are small. The same page also requires an application if the same installer has fitted generation at another property in the same postcode sector, such as PH1 2, within the last 28 days.

Use the G98 or G99 route finder to work out the procedure from the inverter sizes before you sign anything. Do not pay the bulk of the price before the connection route for the inverter is known, because a refused or limited export can change which inverter makes sense.

Routes for a home battery in an SSEN area (SSEN pages, checked 27 Nov 2026)
RouteLimitsWhenForm
G98Total 16 A (3.68 kW) per phase or less, one generatorNotify within 28 days after commissioningG98 Form B
G99 SGI-1Unit up to 32 A design, limited to 16 A; total 16 ANotify after installationForm A3-3
G99 SGI-2Total up to 32 A; export limited to 16 A if neededApply firstForm A1-2
G99 SGI-3Total up to 60 A (14.72 kW); export limited to 32 A if neededApply first, with loop impedance readingsForm A1-2 and FO-NET-CAB-008

How to notify or apply to SSEN

For a G98 job, SSEN's page asks for the G98 Form B within 28 days of commissioning, sent to microgen@sse.com, and its FAQ says your installer should notify on your behalf. It wants the property address and MPAN, the total generation in kW and the inverter type test certificate, whose rating must match the schematic.

For the G99 fast track, applications on Form A1-2 go to G99FastTrack@sse.com. SSEN asks for the installer, installation and generator details, each unit's design capacity, registered capacity and G100 export limit, details of any proposed electricity storage, the MPAN and any existing generation, and a schematic showing the inverter name and rating, the lockable isolators and the boundary between SSEN's equipment and yours. An SGI-3 application also needs the FO-NET-CAB-008 loop impedance measurements.

After commissioning, the installer sends Form A3-2 to the north or south notifications inbox in the table above. SSEN's helpline for these connections is 0800 048 3516, Monday to Friday, 8am to 5pm.

SSEN's own timescales

These are the timescales SSEN states on its pages, not our estimates. Missing attachments are the usual reason a fast track answer takes longer, because the clock in practice starts when the application is complete.

  • G98: Form B within 28 days of commissioning; no approval wait
  • G99 fast track: SSEN says it aims to respond within 10 working days
  • You cannot connect until SSEN confirms its assessment is complete
  • After that, the installer has up to 3 months to install and commission
  • Form A3-2 within 28 days of commissioning
  • A standard G99 application, outside the fast track, can take up to 45 working days for an offer under G99 itself

Export limitation on SSEN's network

An export limitation scheme, tested to the G100 standard, measures power leaving the house and holds the inverters back so export stays under an agreed figure. SSEN says one is not needed when total generation is 3.68 kW or less, or when the export fits within spare network capacity. Where capacity is short it may be required, and SSEN notes it can also mean a faster connection.

SSEN also says that for domestic customers the maximum generation typically ranges between 5 kW and 15 kW, capped by the import or export agreement and by what the local voltage can take. If the installer proposes a large hybrid inverter, ask what export figure has been agreed and get it in writing before the inverter is ordered. Our guide to export limitation and DNO caps explains how a limit changes what the battery can earn.

For an export tariff, SSEN says that below 30 kW your supplier arranges the export MPAN. Keep SSEN's reply with the installation certificate, because the supplier or a later buyer's solicitor may ask for it.

SSEN flexibility schemes and home batteries

Apart from the free packs, we found no SSEN grant for fitted batteries on its pages. What it does run is flexibility: it pays owners of generation, storage and demand to change how much they use or produce when the network asks. Its flexibility page says homes and businesses can earn money this way by registering as a flexibility service provider. The roadmap calls the companies that gather many homes into one service flexibility service providers, sometimes known as aggregators.

SSEN's Flexibility Roadmap of May 2026 names three things that touch home batteries. Smart Signal is a proposed half-hourly, location-specific signal, published ahead of time, meant to guide EVs, heat pumps and home batteries where the local network is tight without bidding. Flex Assure is an independent compliance scheme with a code of conduct for the companies that run household flexibility, and SSEN encourages its providers to join. A separate interim payment service in Load Managed Areas helps keep electric heating flexible as the old radio teleswitch meters are replaced.

None of these is something a householder applies for directly today. If you want a battery that can earn from flexibility, ask the installer and your supplier which tariff or service the battery can join, and whether the provider has signed the Flex Assure domestic code.

On the actual building

The connection form is often the easy part. Use the postcode first, then the local solar yield, then the form, and then look hard at where the battery will go. The cupboard has to be a place you can stand in, at a temperature the datasheet allows, and not an escape route or a hot boiler cupboard. A five-minute video is not a survey.

Before a deposit, get the usable capacity, who holds the warranty, the inverter size and a written note of the G98 or G99 route. If you would rather have the paperwork prepared for you, the grid connection pack turns the route finder's answer into form data, an evidence checklist and letters.

G98 and G99 paperwork

Not sure which form your system needs?

The free route finder works out whether your solar or battery is G98, or G99 SGI-1, SGI-2 or SGI-3, from the inverter sizes. The £19 pack then fills in the form data, the evidence checklist and the letters for your network operator.

Frequently asked questions

How do I get an SSEN home battery pack?

Register for SSEN's Priority Services. SSEN says eligible customers do not need to apply: it assesses needs and local power cut frequency and contacts people who qualify when it is their turn. The packs are aimed at people who are medically dependent on electricity.

Is the SSEN battery pack a home battery I can connect to solar?

No. It is an EcoFlow Delta 3 portable power station of 1,024 Wh, charged from a socket and used to run small devices in a power cut. It is not wired into the house and needs no G98 or G99 paperwork.

Does SSEN give grants for fitted home batteries?

Not that we found on its pages, checked on 27 November 2026. SSEN pays for flexibility from storage through providers, and gives the free packs to some Priority Services customers, but it does not fund the purchase of a fitted battery.

How long does SSEN take to approve a battery?

On the G99 fast track SSEN says it aims to respond within 10 working days of an application. A G98 job needs no approval wait, only Form B within 28 days of commissioning, unless it is a second generator at the property.

Which email address do I send SSEN forms to?

G98 Form B goes to microgen@sse.com. G99 fast track applications go to G99FastTrack@sse.com. Commissioning notifications go to Notifications.northmicrogen@sse.com in Scotland or Notifications.southmicrogen@sse.com in England. In practice your installer sends them.

Is Oxford SSEN or another network?

Oxford is in SSEN's central southern England area, served by Southern Electric Power Distribution. Check the exact postcode anyway, since addresses near a boundary or on a new estate can be on a different network.

Do I need export limitation with SSEN?

Not if total generation is 3.68 kW or less, or the export fits the spare capacity on your local network. Where it does not, SSEN may require a G100 export limitation scheme, typically 16 A under SGI-2 or 32 A under SGI-3.

Want a real price for your home?

Figures here are a guide. An installer still needs to see your fuse board, where the battery will go and whether you want backup. Tell us your postcode and local installers will quote.

Get free quotes