Quick answer
A G99 offer is the network's written permission with conditions, not a gold star. The line that matters is the one that says the kit must not be switched on until the network has agreed, and the number next to export is often smaller than the inverter badge.
Which door you came through
At or below 16 amps per phase, which is 3.68 kW, many house batteries can use G98. That route is connect and notify. You commission, then you tell the distribution network operator (DNO), the company that owns the local wires.
Above 3.68 kW, G99 is the usual door: apply first, switch on only after they agree. A 5 kW hybrid inverter (solar and battery in one box) on a single-phase house is already through it. Plenty of home batteries sold in Britain sit there. It is ordinary, and it is also a reason not to order the kit before the application is in.
The offer comes back from the network that owns the local wires. In Leeds or York that is Northern Powergrid. In Bristol or Exeter it is National Grid Electricity Distribution. A letter headed for the wrong region is the wrong letter.
The kilowatt that is not the brochure
Read the accepted inverter rating and the export limit as two different numbers. The inverter can be allowed to run at 5 kW inside the house while export is capped at 3.68 kW, or lower, if the street is already busy.
That cap is not an insult. It can make the battery more useful, because midday solar that cannot leave the property has to go into the pack or into the kettle. The installer has to commission the limit, not just mention it.
If the offer says a smaller inverter than the one on the quote, the quote is now wrong. Change the equipment schedule before anyone takes a deposit for a model the network has not accepted.
Dates, and the sentence about energising
Look for a validity date. Offers expire. A quote accepted in October for an install in April can outlive the offer, and then the application starts again.
Look for the instruction not to energise until the conditions are met. Switching a 5 kW inverter on because the cupboard is finished, while the offer is still in draft, is how jobs get switched off again.
Some replies ask for a voltage or a fault-level point that only the designer can answer. That is the installer's job to close. Your job is to see that it was closed, and to keep the email.
What you file next to the certificate
Keep the application, the offer, and the commissioning confirmation that the settings match the offer. MCS (Microgeneration Certification Scheme) paperwork does not replace the network letter. Insurers and buyers ask for both.
If an export limiter is part of the design, the schematic should show it. A limiter that exists only in a sentence is not commissioned.
Fast-track or connect-and-notify products exist for some equipment lists. If your installer claims one, ask them to show the product on the network's accepted list and the notification they actually sent. A logo on a datasheet is not that notification.
G98 and G99 paperwork
Not sure which form your system needs?
The free route finder works out whether your solar or battery is G98, or G99 SGI-1, SGI-2 or SGI-3, from the inverter sizes. The £19 pack then fills in the form data, the evidence checklist and the letters for your network operator.
Frequently asked questions
Can I ignore G99 if the battery is only for the house?
No. The inverter is still a generator connected to the supply. Using the energy indoors does not take it outside the connection rules. Export limiting is a condition, not an exemption from applying.
The offer capped export. Did I waste the solar?
Not if the battery is large enough to catch the midday surplus and the limiter is actually set. You lose the chance to sell every spare unit. You do not lose the units you use later in the house.
Who pays if the network wants a bigger study?
Ask before you sign. A normal house battery on a normal street rarely needs a paid network study. If the reply asks for one, that cost should be a written line, and you can still decide to fit a smaller inverter instead.