Quick answer
On our planning timeline, a UK home solar installation takes about two to six weeks from survey to switch-on, and longer when the network operator has to approve the system before it is fitted. The roof work itself usually takes one to two days, with scaffold going up the day before and coming down a few days after. The order is: survey, quote and design, network notification or a G99 application, scaffold, roof fixings, panels, inverter and isolators, commissioning, MCS certificate and handover, then your Smart Export Guarantee application.
- Whole job: about two to six weeks on our planning timeline
- Roof work: usually one to two days on site
- Over 16A (3.68 kW) per phase, apply to the network operator first
- A battery fitted at the same time counts toward that limit
- MCS certificate plus a smart export meter unlock SEG payments
The timeline at a glance
The table is our planning timeline for a straightforward house with a pitched tiled roof. Your installer's diary, scaffold availability, the weather and the network operator decide where you land in each range. The weeks are counted from the survey, and the on site column is the time someone is actually at your house.
| Step | When | On site |
|---|---|---|
| Survey | Week 0 | 1 to 2 hours |
| Quote and design | Week 0 to 1 | None |
| G98 check or G99 application | Week 1 to 3 (fast track) | None |
| Scaffold up | Day before fitting | Half a day |
| Roof fixings and rails | Fitting day 1 | Half a day |
| Panels and DC cabling | Fitting day 1 to 2 | Half to one day |
| Inverter and isolators | Fitting day 1 to 2 | Half a day |
| Commissioning and handover | Last fitting day | A few hours |
| Scaffold down | A few days later | Half a day |
| G98 notice to network | Within 28 days | None |
| MCS certificate | After registration | None |
| SEG application | Once you hold it | None |
- Built from the network operators' published response times and typical installer scheduling; it is a guide, not a promise.
The survey
The surveyor looks at the roof direction, pitch, shading and condition, goes into the loft to see the rafters, and checks the consumer unit, the meter position and where the inverter will hang. If a battery is planned now or later, this is when its location is chosen.
Since 18 June 2026 the MCS solar standard, MIS 3002 version 6.0, has required the roof structure to be checked by a suitably competent person before installation. Some roofs must go to a qualified structural engineer, including roofs pitched under 30 degrees, roofs altered after they were built, and traditional cut timber roofs with hips or valleys. If your roof falls into one of those groups, expect a few extra days for the engineer's report.
Quote, design and planning check
A proper quote shows the panel layout, the inverter, the expected yearly generation calculated by the MCS method, and what is excluded. When you have more than one, line them up using our guide to comparing solar panel quotes.
Most house roofs in England are permitted development, so no planning application is needed. The Planning Portal limits include panels not sitting above the highest part of the roof (chimneys excluded), projecting no more than 200mm from a pitched roof slope, and being sited to limit the effect on the building's appearance. Panels on a listed house in England are outside permitted development, so they need planning permission, and you should ask the council about listed building consent too; conservation areas add limits on walls and roofs facing a highway. New permitted development rules started on 27 August 2026, with a transition period to 27 August 2027. Our guide to solar panels and planning permission covers the detail. Where an application is needed, that wait sits before everything else in the timeline.
Network operator: G98 or G99
This step decides whether the job takes two weeks or two months. Under G98, if the total rating of every generating device at the property is 16A (3.68 kW) per phase or less, the installer connects first and sends the network operator the installation document within 28 days of commissioning. National Grid Electricity Distribution counts the inverter's continuous rating, added up across all devices, whether or not they ever run at full output together.
Above that, the installer applies under G99 before fitting. Most homes go through the fast track: SSEN aims to respond within 10 working days, and National Grid Electricity Distribution says the same for postal and email applications. A fast track G99, which covers most homes, fits inside our two to six weeks. A full G99 can take up to 45 days for a reply: GOV.UK says the network operator will be in touch within 45 days for low voltage devices that must apply to connect. Once approved, SSEN gives the installer up to three months to install and commission. Larger systems may be approved only with an export limit. Your installer handles the forms; you can see which operator covers your street with our DNO lookup, and the full rules are in G98 and G99 explained.
Scaffold
Most pitched roof jobs use scaffold with edge protection, usually put up the day before fitting. HSE guidance says work at height must be properly planned, supervised and carried out by competent people, which is why a ladder alone is rarely used for a full array. Make sure the scaffold firm knows about parked cars, gates and any shared driveway.
Fitting day: fixings, panels, inverter and isolators
On a tiled roof, tiles are lifted, hooks are fixed to the rafters, the tiles go back, and aluminium rails are bolted to the hooks. Slate needs a different fixing, covered in our guide to solar panels on a slate roof. The panels are then clamped to the rails and wired together in strings, and the DC cable is run down through the loft or outside the wall to the inverter.
The inverter is mounted in the loft, garage or utility room, with DC and AC isolators beside it, and connected to the consumer unit. Expect noise on the roof, dust in the loft and a short power cut while the consumer unit is connected. Someone needs to be home to give access to the loft and meter.
Commissioning, MCS certificate and handover
The electrician tests the system, switches it on and sets up the monitoring app. The installer registers the job with MCS, which produces the MCS certificate. Electrical work is signed off through a competent person scheme, so you do not need to apply to building control yourself. If the MCS certificate has not reached you within a few weeks, ask the installer first, then MCS.
- MCS certificate, needed for Smart Export Guarantee payments
- Electrical installation certificate
- Building regulations compliance certificate from the installer's scheme
- Network operator notification or G99 approval
- Panel, inverter and any battery warranties
- Workmanship warranty and any insurance-backed guarantee
- Generation estimate and the generation meter reading at handover
SEG application
GOV.UK sets out what you need: an installation certified through MCS or an equivalent scheme, and a meter that gives half-hourly export readings, which would typically be a smart meter. Ofgem says you can choose any SEG licensee, not only your current supplier, and that a SEG tariff must always stay above zero. Apply as soon as the certificate arrives, because payments are based on metered export. Our guide to the SEG and batteries compares the options.
Solar and battery installed together: what changes
Fitting a battery in the same visit adds little time on the day. The battery goes on a wall indoors or in a garage, so it needs no extra scaffold. Expect roughly an extra half day on our planning timeline for mounting, cabling and setting the charge schedule, a little more if a backup gateway is added.
The paperwork changes more. Network operators count storage in the same total as solar, so the battery can push a G98 job into G99. A worked example using the 16A rule: a 3.6 kW solar inverter plus a separate 3 kW battery inverter adds up to 6.6 kW, about 29A on a 230V supply, which is over the 16A G98 limit and needs a G99 application before fitting. The same panels and battery run through one 3.6 kW hybrid inverter stay at about 16A, so G98 notification after commissioning usually applies. That single choice can move switch-on by several weeks.
VAT is unchanged: HMRC Notice 708/6 zero rates solar panels installed in homes until 31 March 2027, and electrical storage batteries installed in homes have been included in the zero rate since 1 February 2024. GOV.UK also notes that a home battery able to export could be used to benefit from the SEG; ask your tariff supplier how it treats exported battery power. If the budget only stretches to panels now, our guide on whether you can add a battery later explains what to ask for at the survey so the later job is simple.
Checking the system works on day one
A low reading on a grey December day is normal. A system producing well under the estimate on a clear summer day is worth reporting to the installer straight away, ideally before the scaffold comes down.
- Ask the installer to show live generation in the app before they leave
- Check the inverter display shows no error code
- Note the generation meter reading on the handover sheet
- Ask the installer to show you where the cables run and where the isolators are
- Check the AC and DC isolators are labelled
- Compare the first sunny week against the estimate: for a 4 kWp south facing system in Newcastle at a 35 degree pitch, PVGIS gives about 15 kWh a day in June but about 3.5 kWh a day in December
G98 and G99 paperwork
Not sure which form your system needs?
The free route finder works out whether your solar or battery is G98, or G99 SGI-1, SGI-2 or SGI-3, from the inverter sizes. The £19 pack then fills in the form data, the evidence checklist and the letters for your network operator.
Frequently asked questions
How long does it take to install solar panels?
The fitting usually takes one to two days on site. On our planning timeline, the whole process from survey to switch-on takes about two to six weeks, longer if a G99 application or a planning application is needed.
How are solar panels installed on a house?
Scaffold goes up, hooks are fixed to the rafters under lifted tiles, rails go on the hooks, panels are clamped to the rails and wired to an inverter indoors, which connects to the consumer unit through isolators. The system is then tested and commissioned.
Do I need to be home for a solar installation?
Usually yes for the start and the handover, and the installers need access to the loft, the meter and the consumer unit.
Will my power be off during installation?
Briefly, while the system is connected to the consumer unit.
Does adding a battery at the same time slow things down?
Not much on the day, but it can change the paperwork. If the solar and battery inverters together exceed 16A (3.68 kW) per phase, the installer must apply under G99 before fitting, which can add weeks.
Can solar panels be installed in winter?
Yes. Wet or windy days can delay roof work, but installation goes ahead in most seasons.
When can I start getting export payments?
Once you have the MCS certificate, a meter that records half-hourly export, and a SEG contract with a supplier. Apply as soon as the certificate arrives.
Want a real price for your home?
Figures here are a guide. An installer still needs to see your fuse board, where the battery will go and whether you want backup. Tell us your postcode and local installers will quote.
Related guides






Sources
- pbctoday: what MIS 3002 actually requires and who it lets sign it off (MIS 3002 V6.0, mandatory from 18 June 2026)
- MCS Certified
- National Grid Electricity Distribution: G98 connection procedures
- National Grid Electricity Distribution: fast track (G99)
- SSEN: G99 fast track process
- GOV.UK: register energy devices in homes or small businesses (DNO reply within 45 days for low voltage apply to connect)
- legislation.gov.uk: GPDO 2015 Schedule 2 Part 14 (Class A excludes listed dwellinghouses)
- Planning Portal: solar equipment mounted on a house or block of flats
- HSE: work at height, the law
- GOV.UK: building regulations approval
- GOV.UK: Smart Export Guarantee
- Ofgem: Smart Export Guarantee for generators
- GOV.UK: energy-saving materials and heating equipment (VAT Notice 708/6)
- European Commission JRC: PVGIS 5.3 PV performance calculator